MOTORISTS crossing the M48 Severn Bridge may have been wondering why a group of workmen had scaled what is one of Britain's tallest pylons.

A team of eight engineers have completed vital refurbishment work on one of Britain’s tallest anchor pylons on the Welsh side of the Severn Bridge, near Chepstow.

Anchor pylons hold the tension in conductors, which are the wires that carry electricity.

These wires span the River Severn, in a route which runs parallel to the old Severn Bridge that carries the M48 motorway.

The Severn crossing is the longest overhead line river crossing in the UK, spanning nearly two and a half miles across the River Wye and River Severn from pylon to pylon.

The two pylons, that stand either side of the River Severn are the second tallest in the UK, at around 150 metres, and hold the overhead lines clear of the river below.

Work to replace the glass insulators on the Welsh side of the river crossing was completed successfully at the end of last week.

More News

Artist transforming neglected Chepstow underpass

HGV jobs in Newport - this is how much they pay

Andrew Lambert: Body found in Monmouth woodland

Insulators maintain the separation between the pylon steelwork and electricity in the overhead power lines, keeping electricity flowing from power stations and renewable energy sources in South Wales.

The unique design and height of power lines on the Severn Crossing, which were installed in the 1950s has involved specialist equipment to hold the tension weight of the overhead lines.

A 75m lorry-mounted mobile access platform has been used so engineers can access the insulators safely, a 70-metre crane weighing 100 tons has been used to lift the heavy equipment into place.

Gareth Davies, Project Engineer for National Grid’s Overhead Line Team said: “This project is just part of the routine work we do every day to keep the electricity network safe.

"There are around 22,000 pylons stretching over more than 7,700km of high-voltage overhead lines in National Grid’s network, so we have engineers working round-the-clock making sure we keep the lights on.

"The work took five days to complete and was carefully planned for months so the insulators could be replaced quickly and safely without disrupting electricity supplies.”